Hoe Valley School
-
Location
UK
-
Voltage
11 kV
-
Completion
2018
Client Challenges
Hoe Valley School had a priority requirement for the design & build of an 11 kV substation to support the new school and sports complex development
Tight timescales in line with client schedules for school term openings
Adherence to Client, UKPN (DNO) and ESP (DNO) Specifications
H&MV Solution
H&MV Project Managed the design of DNO Substation, contestable HV cable route, earthing, LV main cable route, street lighting, civil & electrical works, installation and commissioning.
Utility Liaison & management
Delivered safely and on time
Scope included 11kV cable laying, jointing and termination, LV cable laying, jointing and termination, Commissioning of all installed equipment and energisation to client LV switch room.
Installed equipment included:
– GRP substation enclosure with brick effect finish, adopted by UKPN/ESP.
– Lucy Sabre VRN2a MV switchgear.
– Efacec 1000kVA distribution transformer.
– Lucy Aculock transformer mounted 1600A ACB LV distribution cabinet.
– Lucy Electric Gemini 3 type RTU.
– 1km of 185/300mm2 CU triplex cable including X8 joints and X2 terminations.Project Management and Commissioning of electrical installation.
Produce a complete set of electrical as built drawings and a safety handover file.
Responsible for issuing the Integrated Test Plans (ITPs), Construction Management Plans, Quality Plans, Safety Management Plan and Temporary Works Register
Daily toolbox talks, weekly progress and safety meetings, issue and risk management along with regular status reporting