110/21 kV Data Centre

Case Study:

Project Location.

Client Challenges.

The client was developing a data centre in Kouvola, Finland, with an ambitious power-on deadline. To meet this critical timeline, the client required specialist high-voltage engineering support and accelerated project delivery.

Our Solution.

H&MV Engineering was appointed as turnkey design and build contractor for the offsite high-voltage substation, grid connection route and onsite HV/MV infrastructure.

Working collaboratively with the client’s design team, we rapidly developed the high-level concept design for the TSO Fingrid connection and main HV/MV data centre infrastructure. Our team quickly identified and specified long-lead equipment, which was critical to achieving the power-on date.

Despite the highly ambitious delivery schedule, H&MV Engineering leveraged our established supply chain relationships to secure production slots for power transformers and switchgear, ensuring the project remained on track to meet the client’s demanding timeline.

Similar Projects.

Ready to start your Data Centre Project?