110/20 kV Data Centre

Case Study:

Project Location.

Client Challenges.

The client required a 42 MW data centre to be built on a greenfield site 20 km south of Berlin with a 110/20 kV substation. German building codes and local regulations, as well as communication, proved a challenge for the client.

Our Solution.

  • As Principal Contractor, H&MV Engineering planned, managed, monitored and coordinated the entire construction phase of the on-site substation, off-site cable route and feeder mast works. H&MV Engineering’s scope of works was divided into the following principal phases: design, permitting, easements and wayleaves, construction, commissioning and handover.
  • This included a 110 kV outdoor air insulated substation and associated switchgear. The substation was connected to the local electricity grid using a double circuit 110 kV underground cables from the overhead line to two 70 MVA 110/20 kV transformers.
  • Liaison and communication, as well as early engagement with the client and e.dis (DNO), ensured this project was delivered on time.

Similar Projects.

Ready to start your Data Centre Project?